PART 1 — GENERAL
1.1 Scope of Work
This section specifies the supply, installation, programming, testing, commissioning and handover of a complete analogue addressable fire detection and alarm system for [project name / building], comprising [number of buildings] building(s) and [number of floors] floors with an approximate protected area of [area in m²]. The work includes, but is not limited to:
- Main and sub fire alarm control and indicating equipment (CIE), networked where more than one panel is required.
- Power supply equipment, standby batteries and battery chargers.
- Addressable loop devices: smoke, heat and multi-sensor detectors, manual call points, short-circuit isolators, input/output modules, sounders, visual alarm devices and combined devices.
- Repeater panels and, where specified, a graphical monitoring workstation.
- Fire-resistant cabling, containment, labelling and all accessories.
- Interfaces with HVAC, lifts, access control, public address/voice evacuation, fire suppression and other building systems as defined in the cause-and-effect matrix.
- Design calculations, shop drawings, testing, commissioning, training, documentation and the warranty period.
The system shall be designed and installed to the code designated for the project: [NFPA 72 / BS 5839-1, category [L1 / L2 / L3 / M / P1]], together with the requirements of the Egyptian fire protection code and the Civil Defence authority having jurisdiction.
1.2 Related Sections and Systems
- Electrical power supply: dedicated, labelled final circuit 220–240 V AC, 50 Hz from the essential (generator-backed) supply.
- Public address and voice evacuation system.
- Access control system (fail-safe release of doors on escape routes).
- HVAC and smoke management systems (fan shutdown, smoke and fire damper control, smoke extract and stair pressurisation).
- Lifts (recall to the designated level).
- Fire suppression systems (sprinkler flow switches, valve monitoring, gaseous extinguishing panels, fire pumps).
1.3 Reference Standards
The latest editions of the following standards apply. Where requirements conflict, the stricter requirement or the approved project code governs.
- NFPA 72 — National Fire Alarm and Signaling Code.
- BS 5839-1 — Fire detection and fire alarm systems for buildings. Code of practice for design, installation, commissioning and maintenance of systems in non-domestic premises.
- EN 54-2 — Control and indicating equipment.
- EN 54-3 — Fire alarm devices. Sounders.
- EN 54-4 — Power supply equipment.
- EN 54-5 — Heat detectors. Point detectors.
- EN 54-7 — Smoke detectors. Point detectors using scattered light, transmitted light or ionization.
- EN 54-11 — Manual call points.
- EN 54-13 — Compatibility and connectability assessment of system components.
- EN 54-17 — Short-circuit isolators.
- EN 54-18 — Input/output devices.
- EN 54-23 — Fire alarm devices. Visual alarm devices.
- EN 54-29 — Multi-sensor fire detectors. Point detectors using a combination of smoke and heat sensors.
- EN 50200 — Method of test for resistance to fire of unprotected small cables for use in emergency circuits.
- IEC 60332-1, IEC 61034 and IEC 60754 — flame propagation, smoke density and halogen/acid gas tests for cables.
- IEC 60529 — Degrees of protection provided by enclosures (IP code).
- The Egyptian fire protection code and the requirements of the Civil Defence authority.
1.4 Definitions
- CIE: Control and indicating equipment (fire alarm control panel).
- Loop / SLC: Addressable signalling line circuit starting and ending at the CIE.
- Zone: Subdivision of the premises used for indication of the location of a fire.
- Cause-and-effect matrix: Table defining the outputs triggered by each input or group of inputs.
- VAD: Visual alarm device (beacon/strobe).
- Engineer: The consultant or client representative approving the work.
1.5 Submittals
- Product datasheets and certificates (EN 54 certificates of constancy of performance or equivalent listings) for every device, with compatibility confirmation per EN 54-13 or the manufacturer's compatibility list.
- Shop drawings: device layouts on architectural plans, zone plans, loop routing, isolator locations, riser diagram and panel network diagram.
- Calculations: battery capacity for every CIE and power supply, loop loading and voltage drop for every loop, sounder and VAD coverage, and cable sizing.
- Draft cause-and-effect matrix for approval before programming.
- Samples of detectors, call points, sounders and cables when requested.
- Test and commissioning procedures and blank test sheets.
- As-built drawings, programming backup, operation and maintenance manuals at handover.
1.6 Quality Assurance
- The contractor shall be an authorised installer of the offered system with at least [5] years' experience and [3] completed projects of similar size, and shall hold the licences required by the Civil Defence authority.
- Design, programming and commissioning shall be carried out by engineers trained and certified by the manufacturer.
- The manufacturer shall operate a quality management system certified to ISO 9001 and shall have a local agent providing technical support and spare parts in Egypt.
- All loop devices, panels and power supplies shall be from one manufacturer or certified as compatible.
1.7 Delivery and Storage
Equipment shall be delivered in original sealed packaging and stored in a dry, clean area. Detector dust covers shall remain fitted until dust-generating construction work is complete. Batteries shall be stored and charged per the manufacturer and be less than [6] months old at installation.
1.8 Warranty
The complete system shall be warranted for [24] months from the date of final acceptance, covering parts, labour and site visits. Faults affecting fire detection or alarm shall be attended within [4] hours and other faults within [24] hours. Preventive maintenance visits shall be carried out every [3] months during the warranty period.
1.9 Spare Parts and Maintenance
- Spare devices: [5%] of each detector type, [2%] of call points, sounders and modules (minimum one of each), and one set of panel fuses.
- One detector test kit (smoke and heat heads, poles, removal tool).
- The supplier shall guarantee availability of spare parts for at least [10] years.
PART 2 — PRODUCTS
2.1 System Description and Architecture
- The system shall be an analogue addressable system in which each detector reports its analogue value to the CIE, and the CIE makes the alarm decision with drift compensation and adjustable sensitivity.
- Each device shall have its own address and a programmable text label of at least [32] characters identifying its exact location.
- Loops shall be wired as Class A pathways per NFPA 72 (loop returned to the panel), with short-circuit isolators so that a single open circuit or a single short circuit on a loop does not cause the loss of more than the devices between two adjacent isolators. This corresponds to the former Style 7 designation for signalling line circuits. Under BS 5839-1 the same loop arrangement shall ensure that a single fault does not remove protection from more than one zone.
- Where Class X performance is required by the approved code, the pathway shall continue to operate during a single open, a single ground fault and a wire-to-wire short.
- Loop loading at handover shall not exceed [80%] of the loop's device and current capacity, leaving [20%] spare capacity.
- Where more than one CIE is provided, panels shall be connected on a fault-tolerant peer-to-peer network so that any panel or the main panel can display and control events from the whole network, according to the access levels.
- Zone size shall not exceed [2,000 m²] floor area per zone and one floor per zone unless the approved code permits otherwise.
2.2 Control and Indicating Equipment (CIE)
- Certified to EN 54-2 with power supply to EN 54-4 (or listed to the equivalent standard approved for the project).
- Loop capacity: [2 / 4 / 8] loops installed, expandable to at least [8] loops, each loop supporting at least [125] detectors and [125] modules or [250] addresses.
- Display: backlit LCD of at least [8] lines × 40 characters, or touch screen, with Arabic and English operation where available.
- Indications: fire, fault, disablement, test, supply on, system fault, and zone LEDs for at least [number of zones] zones.
- Controls: acknowledge, silence/resound sounders, reset, evacuate, and delay on/off, protected by at least [3] access levels with passwords or key switch.
- Event log of at least [10,000] events with date and time, accessible from the front panel and downloadable.
- Programmable logic for cause-and-effect, including AND/OR functions, coincidence (two-detector) dependencies, investigation delays and day/night sensitivity.
- Automatic detector testing and maintenance alerts for contaminated detectors.
- At least [2] monitored conventional sounder circuits and [2] programmable relay outputs on the panel.
- Interface for remote monitoring and for high-level integration with the BMS or graphics workstation using an open protocol [BACnet / Modbus] where specified.
- Metal enclosure, IP30 minimum, lockable, surface or flush mounted.
2.3 Power Supply and Batteries
- Mains supply 220–240 V AC, 50 Hz, with supply and earth-fault monitoring; power supply equipment to EN 54-4.
- Sealed valve-regulated lead-acid batteries with temperature-compensated charging and battery fault monitoring.
- Battery capacity shall be calculated for each CIE and power supply using the BS 5839-1 method:
C = 1.25 × (T1 × I1 + D × T2 × I2)
- C = minimum battery capacity at the 20-hour discharge rate (Ah).
- T1 = standby duration in hours: [24 h, or as required by the approved code / Engineer].
- I1 = total standby (quiescent) current in amperes.
- T2 = alarm duration in hours: [0.5 h, or as required by the approved code / Engineer].
- I2 = total alarm current in amperes.
- D = de-rating factor for the battery at high discharge currents: 1.75 for the BS 5839-1 method (when T2 = 0.5 h the term becomes D × I2 / 2).
- 1.25 = factor for battery ageing and capacity loss over its service life.
The selected battery shall be the next standard size above C. Where the project code is NFPA 72, the standby and alarm durations shall be those stated by NFPA 72 for the system type, and a safety margin of not less than [20%] shall be added.
2.4 Optical Smoke Detectors
- Analogue addressable point detectors using the scattered-light principle, certified to EN 54-7.
- Integral or base-mounted short-circuit isolator where required by the loop design.
- Bi-colour or red LED visible through 360°, flashing on polling where enabled and steady on alarm.
- Insect screen, drift compensation and contamination warning.
- Common base for all detector types, with a remote indicator output.
- Operating range at least −10 °C to +55 °C, up to 95% RH non-condensing.
2.5 Heat Detectors
- Analogue addressable point heat detectors certified to EN 54-5, programmable as fixed temperature or rate-of-rise.
- Class selection to suit ambient temperature: [A1 / A2 / B / C] (A1R for general areas, higher classes for kitchens and plant rooms).
2.6 Multi-Sensor Detectors
- Analogue addressable detectors combining optical smoke and heat sensing, certified to EN 54-29 (and EN 54-7 / EN 54-5 for the individual modes where applicable).
- Programmable operating modes (smoke only, heat only, combined) selectable per device and by time schedule.
2.7 Manual Call Points
- Addressable, Type A (direct operation) certified to EN 54-11, with resettable operating element and test key.
- Red, with standard fire symbol and bilingual (Arabic/English) labelling where required.
- Hinged transparent protective cover where accidental operation is likely; IP65 weatherproof version for outdoor and wet areas per IEC 60529.
2.8 Sounders and Visual Alarm Devices
- Loop-powered addressable sounders certified to EN 54-3, with at least [two] selectable tones (alert and evacuate) and output adjustable up to at least [100] dB(A) at 1 m.
- All sounders shall be synchronised across the building.
- Visual alarm devices certified to EN 54-23, category [C (ceiling) / W (wall)] with the declared coverage volume, red or white flash, synchronised.
- Combined sounder-VADs and sounder bases may be used where approved.
- Sound levels: not less than [65 dB(A), or 5 dB above any noise likely to persist for more than 30 s] for BS 5839-1, or [15 dB above average ambient sound level] for NFPA 72 public mode; [75 dB(A)] at the bedhead in sleeping areas.
- VADs shall be provided in noisy areas (ambient above [90] dB(A)), in areas where hearing protection is worn, in toilets and in areas used by people with hearing impairment.
2.9 Short-Circuit Isolators
- Certified to EN 54-17, either as separate modules or built into detector bases and devices.
- Located so that a short circuit removes not more than [32] devices, and at every zone boundary and floor entry of the loop.
- LED indication of the isolated state.
2.10 Input/Output Modules
- Addressable modules certified to EN 54-18, available as monitored input, relay output (volt-free contacts at least [2 A at 30 V DC]), and monitored supervised output for conventional sounders or extinguishing release interfaces.
- Mains-voltage loads shall be switched only through interposing relays installed in a separate enclosure with 220–240 V AC rated contacts.
- Modules shall be installed within [1 m] of the controlled equipment where possible, and labelled with the controlled function.
2.11 Repeater Panels and Graphics
- Repeater panels with LCD display and the same basic controls as the main panel (subject to access level), located at [main entrance / security room / building management office].
- Where specified, a graphical workstation showing floor plans, device icons and events, with Arabic/English interface and UPS.
2.12 Fire-Resistant Cables
- Fire-resistant, low-smoke zero-halogen (LSZH) cable, 2-core screened, minimum [1.5 mm²] for loops and sounder circuits, or as required by the voltage-drop calculation.
- Fire performance class according to the approved code: [standard / enhanced fire-resisting cable per BS 5839-1] or circuit integrity rating required by NFPA 72 for the survivability level of the building; tested to EN 50200.
- Flame propagation, smoke density and acid gas tests to IEC 60332-1, IEC 61034 and IEC 60754.
- Red outer sheath, used only for the fire alarm system.
PART 3 — EXECUTION
3.1 Examination
Before installation, the contractor shall check ceiling heights, ceiling voids, beams, air-conditioning diffusers and room uses against the approved shop drawings, and shall report any conflicts to the Engineer in writing. Devices shall be coordinated with lighting, HVAC and sprinklers.
3.2 Installation
- Installation shall comply with the approved project code ([NFPA 72 / BS 5839-1]), the Egyptian fire protection code and the manufacturer's instructions.
- Detector spacing and coverage shall follow the approved code (for example, under BS 5839-1 a maximum horizontal distance of 7.5 m to a smoke detector and 5.3 m to a heat detector on flat ceilings; under NFPA 72 the listed spacing). Detectors shall be at least [1 m] from air supply diffusers and [0.5 m] from walls and light fittings.
- Detectors shall be provided in ceiling and floor voids where required by the code and the void depth.
- Manual call points shall be installed at [1.4 m ± 200 mm (BS 5839-1) / 1.07–1.22 m (NFPA 72)] above finished floor level, at every storey exit and final exit, with maximum travel distance as required by the approved code.
- CIE and repeaters shall be installed at the fire brigade access point, with the top of the display not higher than [1.8 m].
3.3 Cabling and Labelling
- Cables shall be installed in dedicated containment or fixed with fire-rated metal clips at intervals not exceeding [300 mm] horizontally; plastic cable ties shall not be the only means of support.
- Outgoing and return legs of a loop shall follow different routes where practicable so that a single incident does not damage both.
- No joints except in labelled, red junction boxes; cable screens shall be continuous and earthed at the panel only.
- Insulation resistance shall be measured before connecting devices and shall not be less than [2 MΩ].
- Every device shall carry its address label, every cable shall be labelled at both ends, and every junction box shall be marked "Fire Alarm".
3.4 Configuration and Programming
- Programming shall follow the approved cause-and-effect matrix. As a minimum the matrix shall cover the inputs and outputs below:
| Input | Output |
|---|---|
| Any detector or call point in a zone | Alarm on CIE and repeaters; sounders and VADs per evacuation strategy [single-stage / phased] |
| Fire alarm in any zone | Shut down AHUs and fans serving the zone; close fire/smoke dampers |
| Fire alarm in any zone | Start smoke extract and stair pressurisation fans |
| Fire alarm (or lift lobby detector) | Lift recall to the designated level [ground floor / alternative floor] |
| Fire alarm | Release fail-safe access-controlled doors on escape routes |
| Fire alarm | Trigger PA / voice evacuation messages per zone and mute background music |
| Sprinkler flow switch | Fire alarm for the related zone |
| Valve tamper switch / pump fault | Fault or supervisory signal only |
- Interfaces shall be monitored where the code requires; interface outputs shall be fail-safe where loss of the link must cause the safe state (e.g. door release).
- Device labels shall use room names and numbers agreed with the client, in [English / Arabic].
- A software backup of the final configuration shall be handed to the client.
3.5 Testing and Commissioning
- Cable tests: continuity, insulation resistance and earth-fault tests for every loop and circuit, recorded on test sheets.
- Every device shall be tested individually: smoke detectors with test smoke, heat detectors with a heat source, multi-sensors in each active mode, call points with the test key. The address, location text and response at the CIE shall be recorded for each device.
- Loop integrity tests: open circuit and short circuit applied at selected points to verify isolator operation and Class A performance.
- Sound pressure level measurement in every room and area with sounders operating; values recorded against the design levels. VAD coverage checked.
- Full cause-and-effect test: each output in the matrix operated from at least one input and witnessed with the HVAC, lift, access control and PA contractors.
- Power tests: mains failure, battery standby test for the calculated duration or a verified calculation by discharge test, and charger operation.
- Network tests: loss of a network link and of a panel, verifying correct fault reporting.
- Acceptance: final witnessed test with the Engineer and, where required, the Civil Defence authority. Deficiencies shall be corrected and retested at the contractor's cost.
3.6 Training
The contractor shall provide [2] days of operator training for security and facility staff (alarm handling, reset, disablements) and [3] days of technical training for maintenance staff (testing, device replacement, basic programming), in Arabic.
3.7 Documentation and Handover
- As-built drawings (printed and editable electronic files) showing every device with its address.
- Final cause-and-effect matrix, battery and loop calculations, and configuration backup.
- Completed test sheets for every device, and commissioning and acceptance certificates.
- Operation and maintenance manuals, zone chart mounted next to the CIE, and logbook.